In Netweaver BI 2004s we can find many new features in process chains. Below I have listed some of them
Copying of process chains:In BI 2004s there is a copy option in the process chain menu.
Go to RSPC -----> Process chain ----> Copy. Enter the technical name and description, save it and click on refresh button. You can see the new process chain in the list.
Client dependent: We have a option of assigning a particular process chain to a particular client.
Go to RSPC ----> Process chain ----> Attributes. Enter client id and save it. Once you assign, the process chain can only monitored in this client. Note: Process variants which are used in one client will not be used in other client.
Display mode: Display, here in BI 2004s we don't have locking issues. One user may change the process chain while the other is just displaying it. Process chain can be scheduled in display mode.